rmqwerty Registered: April 12, 2007
Posts: 2
|
|
| April 12, 2007 at 07:01 PM |
|
Reply with quote | #1 |
I have created a map and all the Activities under the Task Complete section are "non actionable". It does not let me change it to an actionable item with a complete %. Is there any way to make it actionable or do I need to recreate the whole map over again?
Thanks, |
| |
NickDuffill
Moderator
Registered: Dec 10, 2004
Posts: 287
|
|
| April 12, 2007 at 08:33 PM |
|
Reply with quote | #2 | Hello
What has probably happened is you used a map template with no % complete Map Markers in it, or have deleted the % complete Map Markers.
To fix this, open the Map Markers task pane, right-click on the "Task Complete" group heading, choose "New Task Percentage" and add some of the other percent complete markers.
Then ResultsManager will let you set the actions to other values.
Best regards __________________ Nick Duffill
Gyronix |
| |
rmqwerty Registered: April 12, 2007
Posts: 2
|
|
| April 12, 2007 at 08:43 PM |
|
Reply with quote | #3 |
Yes that was it! Thanks for the quick response. |
| |